Views: 0 Author: Site Editor Publish Time: 2022-05-23 Origin: Site
Fiberglass Geogrid is an excellent geosynthetic material, which is often used in the field of building materials processing. For example, the product can be seen during the operation and construction of asphalt pavement.
What are the intermediate construction steps of Fiberglass Geogrid?
What are the finishing steps of Fiberglass Geogrid construction?
What is the fixing method of Fiberglass Geogrid?
1. After the first layer of Fiberglass Geogrid is completed, start to fill in the second layer of 0.2m thick medium (coarse) sand. The method is to transport the sand to the construction site and unload it on the side of the roadbed. Then use a bulldozer to push forward. After 0.1m is filled within 2 meters on both sides of the roadbed, the first layer of Fiberglass Geogrid is folded up and filled with 0.1m of medium (coarse) sand. It is forbidden to fill and advance in the middle on both sides, and all kinds of machinery are prohibited Filling the Fiberglass Geogrid with medium (coarse) sand can be used to ensure that the geogrid is flat, without drums or wrinkles. After the second layer of medium (coarse) sand is leveled, horizontal measurement should be carried out to prevent filling. If the thickness is not uniform, use a 25T vibratory roller to static pressure twice after it is smoothed.
2. The construction method of the second layer of Fiberglass Geogrid is the same as that of the first layer. Finally, 0.3m of medium (coarse) sand is filled. The filling method is the same as that of the first layer. After two times of static pressure with a 25T roller, the roadbed base and the reinforcement is processed.
3. After the middle (coarse) sand is rolled in the third layer, two Fiberglass Geogrid sheets are laid on both sides of the slope along the longitudinal direction of the line, overlapped by 0.16m, and connected by the same method, and then start earthwork and lay the Fiberglass Geogrid performs side slope protection. It is necessary to measure the laid sidelines of each layer, and each side must ensure that the geogrid is buried 0.10m inside the slope after the slope is repaired.
1. When filling two layers of soil on the side slope Fiberglass Geogrid, that is, when the thickness is 0.8m, a layer of geogrid must be laid on both sides at the same time.
2. After the subgrade is filled, the slope should be repaired in time, and dry rubble protection of the slope foot should be carried out. In addition to the 0.3m widening of each side of the subgrade, 1.5% of the settlement amount should be reserved.
Fiberglass Geogrid is fixed by nail fixing method, one end is fixed with fixing nails and fixed on the spilled bitumen substructure. The nails can be shot with a hammer or gun, and then the geogrid is fixed vertically and fixed in sections. The distance of each section is 2-5 meters, and the interval of concrete pavement can be divided according to the interval of joints. The nails are located at the seams.
Feicheng Lianyi Plastic Co., Ltd. has worked on the production of Fiberglass Geogrid for several years. You can find the best Fiberglass Geogrid in this company.